Tydal’s “breathing” AI data centre is designed to ease the grid, not just draw from it

3 min read

tydal-180mw

The former crypto site in Trøndelag will pair 180 MW of capacity with what its chairman calls the Nordic region’s largest battery, so it can cut its draw from the grid when the power system is under strain.

Tydal Data Center, owned by Bitdeer, is being converted from bitcoin mining into one of Europe’s largest AI facilities. In August, Bitdeer signed a 16-year colocation lease through its subsidiary Tydal Data Center AS with Volta Tydal AS, a subsidiary of Volta. Volta’s customer at the site will be a leading AI lab, with Dell Technologies as the technology provider, and the site will deliver 121 IT megawatts supported by an estimated 133 gross MW. Bitdeer has not named the AI lab. According to Digi.no, Bloomberg has reported that it is Anthropic

A data centre that can step back

In interviews with Teknisk Ukeblad and Digi.no this week, chairman Haakon Bryhni described the design as a “breathing” data centre. The site has been built to support the grid rather than as cheaply as possible. Among other things, it will have the Nordic region’s largest battery, sized to carry the data centre’s full 180 MW. When the grid is under heavy load, the centre can reduce its power draw, for example by switching to batteries.

This is the kind of behaviour Statnett now wants to set rules for. When it paused new grid reservations for data centres on 9 November, the transmission system operator pointed to large and rapid load changes. It said it would set functional requirements covering how quickly consumption can change and when data centres must stay connected during disturbances.

Others in the industry are making the same argument. Skygard CEO Trond Johannessen told Teknisk Ukeblad that data centres should take more responsibility for contributing to the energy system, and called for stronger incentives for power development, energy storage and waste heat recovery.

Scale of the site

Bryhni has said the facility is already energised and connected directly to Norway’s hydropower grid. Bitdeer is also at an early stage with two more data halls totalling 47 gross MW, outside the Volta lease, with a target completion date in the second half of 2027.

Bryhni expects around 50,000 GPUs on site. He puts the total investment at around NOK 500 billion, since Volta has said its investment is roughly ten times the value of the lease. He also plans to give away two million GPU hours, half to Simula Met and NTNU and the rest to public bodies and start-ups. 