Statnett pauses new grid reservations for data centres until August 2027

3 min read

Norway’s transmission system operator Statnett has introduced a temporary halt on new grid capacity reservations for data centres. The measure, announced on 9 November 2026, covers new connection reservations for data centres, the processing of new applications for approval of facility functionality under Section 14 of the Regulations on System Responsibility (fos), and applications already received for direct connection to the 420 kV grid.

Why Statnett is pausing

Statnett’s reasoning is technical rather than about energy volumes alone. Data centres have characteristics that can affect secure and stable system operation, including large and rapid changes in load, software-controlled consumption and higher sensitivity to disturbances. The operator says it needs tools and a framework so that new connections have manageable consequences for the power system.

The numbers explain the urgency. According to Statnett, 800 MW of data centre capacity is connected today, 4,200 MW has reserved capacity, 9,100 MW is in the capacity queue, and there are requests for a further 18,000 MW. Peak power consumption in Norway is just over 25,000 MW.

What happens next

The pause is expected to be lifted by 1 August 2027 at the latest, but it applies until Statnett has set functional requirements approved by the energy regulator RME and mechanisms for compliance are in place. Examples of such requirements include when data centres must not disconnect from the grid during disturbances, how quickly their consumption can change, and technical measures to reduce the risk of oscillations in the grid. The requirements will go out for consultation, and Statnett will coordinate them with other Nordic system operators and ENTSO-E.

Who is affected

This is not a general stop. Existing connections are not affected, facilities with approved functional requirements can still be connected, and applications already received for facilities in the regional grid with planned commissioning in the near future are not stopped. Statnett will also consider some applications for smaller facilities up to 1 August 2027. At the same time, freed-up capacity will not be given to other customers as long as it could go to data centres ahead in the queue.

Projects with a connection date before August are still in different positions. Digi.no reports that only 6 of 24 reservations up to 1 August can proceed as normal.

A wider regulatory shift

The pause came on the same day as the government signalled tighter oversight of the sector [link: Norway plans stricter regulations for data centres]. The government said it will investigate and implement measures to ensure controlled growth of socially beneficial data centres, including regulatory changes allowing Statnett to set conditions for grid connection and a licensing scheme for data centres. As Digitalisation Minister Torgeir Micaelsen put it, “We want data centers in Norway, but we can’t have all types of data centers.”