Stargate Norway (Kvandal)

Under construction Narvik, Nordland AI-HPC

CONFIRMED · LAST VERIFIED 29 OCT 2026

230 MW
IT power
not published
Building area
not published
Peak construction jobs
Q4 2026
First operational (est.)
Open in Google Maps (opens in a new tab)
Site 68.57856° N, 17.62335° E

About this project

AI campus at Kvandal outside Narvik, set up by Nscale and Aker as a 50/50 joint venture, with OpenAI as the first customer. The plan is 230 MW of hydro-powered capacity with direct-to-chip liquid cooling and 100,000 NVIDIA GPUs by the end of 2026, with ambitions to add another 290 MW. Contractor HENT has been engaged for buildings totalling 100 MW on the Kvandal North campus.

Timeline

  1. JUL 2025 Announced — current stage
  2. Q4 2026 First operational ESTIMATED

Companies involved

Investor & operator

Gallery

Sources

  1. 1. Nscale, Aker and OpenAI to establish Stargate Norway — Aker ASA , 31 Jul 2025. www.mfn.se/… accessed 29 Oct 2026
  2. 2. HENT enters preliminary agreement with Nscale for two additional data centres in the Narvik region — Sentia , 23 Jun 2026. www.placera.se/… accessed 29 Oct 2026

Vehicle rental for contractors working in Narvik

Long-term rental of vans, pickups and crew cars on monthly terms, delivered to sites across Narvik. One monthly price covers servicing and tyres.

  • Monthly terms
  • Delivery to site
  • Service and tyres included

    Fields marked * are required.

    OsloBilutleie.no PORTAL PARTNER