GreenScale Tonstad
REPORTED · LAST VERIFIED 30 OCT 2026
- not published
- IT power
- not published
- Building area
- not published
- Peak construction jobs
- 2027
- First operational (est.)
About this project
Tonstad DataPark is a planned four-building data centre campus at Tonstad in Sirdal, in the hydropower heartland of Agder. The 42-hectare site was developed for five years by local entrepreneur Tore Knapskog, who secured 300 MVA of grid capacity approved by Glitre Nett and Statnett before selling the project to GreenScale in June 2025.
GreenScale, a platform launched by the investment firm DTCP to build 1 GW of European capacity, expects to invest more than EUR 2.5 billion in the campus. The first capacity is targeted for 2027. Tonstad sits close to the Sira-Kvina hydropower system, one of the largest in Norway, which gives the site direct access to renewable power. No anchor customer has been announced.
Timeline
- JUN 2025 Announced — current stage GreenScale (DTCP) buys the project with 300 MVA of approved grid capacity and announces a four-building campus. Source
- 2027 First operational ESTIMATED
Sources
- 1. GreenScale acquires Tonstad DataPark in Norway, plans 300MW data center campus — Datacenter Forum , 10 Jun 2025. www.datacenter-forum.com/… accessed 30 Oct 2026
- 2. GreenScale acquires land in Norway, targets 300MW data center campus — DCD , 5 Jun 2025. www.datacenterdynamics.com/… accessed 30 Oct 2026
Vehicle rental for contractors working in Sirdal
Long-term rental of vans, pickups and crew cars on monthly terms, delivered to sites across Sirdal. One monthly price covers servicing and tyres.
- Monthly terms
- Delivery to site
- Service and tyres included