Green Mountain TEL-Rjukan
Operational Tinn, Telemark
Colocation
CONFIRMED · LAST VERIFIED 29 OCT 2026
- 50 MW
- IT power
- not published
- Building area
- not published
- Peak construction jobs
- Jan 2014
- Operational since
Site
59.87891° N, 8.59411° E
About this project
Colocation campus in Rjukan, the historic hydropower town in Telemark, in operation since 2014. Four buildings with about 29,000 m² of space let customers start with single racks and grow in 2 MW modules. Green Mountain states a maximum IT capacity of 50 MW, fed by two independent grid supplies.
Timeline
- JAN 2014 First operational — current stage
Companies involved
Investor & operator
- Green Mountain AS Operator
Sources
- 1. TEL-Rjukan — data centre profile — Green Mountain . greenmountain.no/… accessed 29 Oct 2026
- 2. Register of data centre operators — Nkom . nkom.no/… accessed 29 Oct 2026
Vehicle rental for contractors working in Tinn
Long-term rental of vans, pickups and crew cars on monthly terms, delivered to sites across Tinn. One monthly price covers servicing and tyres.
- Monthly terms
- Delivery to site
- Service and tyres included