Google Skien (Gromstul)

Partially operational Skien, Telemark Hyperscale

CONFIRMED · LAST VERIFIED 29 OCT 2026

not published
IT power
not published
Building area
not published
Peak construction jobs
Q4 2026
Operational since
Open in Google Maps (opens in a new tab)
Site 59.27062° N, 9.53355° E

About this project

Google's first Norwegian data centre, on a site at Gromstul about 10 km north of Skien that Google bought in 2019; the Norwegian developer company is WS Computing AS. The site was zoned for power-intensive industry in 2018 and Google has been allocated 240 MW for the first phase. Google broke ground on the first building in 2024.

Timeline

  1. Q4 2026 First operational ESTIMATED

Workforce and construction scale

100
Permanent jobs

Sources

  1. 1. Detailed zoning plan for gbnr. 11/1 — Datasenter på Gromstul (municipal assessment) — Skien kommune . www.skien.kommune.no/… accessed 29 Oct 2026
  2. 2. Google breaks ground on Norway data center — DCD . www.datacenterdynamics.com/… accessed 29 Oct 2026

Vehicle rental for contractors working in Skien

Long-term rental of vans, pickups and crew cars on monthly terms, delivered to sites across Skien. One monthly price covers servicing and tyres.

  • Monthly terms
  • Delivery to site
  • Service and tyres included

    Fields marked * are required.

    OsloBilutleie.no PORTAL PARTNER