ASP Data Center is considering a listing on Oslo Børs and is gauging interest from potential investors, digi.no reports, citing Bloomberg and Dagens Næringsliv. Arctic Securities and DNB Carnegie are helping with the preparations. A listing could come this year, but no decision has been taken.
Growing pipeline in western Norway
The company runs the fully let K11 data centre at Forus, built by Equinor in 2013, where a second phase of 6 MW is due in 2027. It is also converting a former clothing factory at Dale in Vaksdal into a 23 MW site and has agreed a land deal with Suldal municipality for a greenfield campus of up to 100 MW, with conditions that rule out crypto mining.
ASP has already raised NOK 1.6 billion in bonds this autumn to support its growth, according to the company.